Formula used
Cubic yards = [length × width × (depth ÷ 12) ÷ 27] × (1 + waste ÷ 100); tons = cubic yards × density
Worked asphalt example
Asphalt Calculator example: 28.4 ft × 14.4 ft × (4 in ÷ 12) ÷ 27 = 5.05 yd³ before allowance. After 10% allowance, the order basis is 5.55 yd³, or 11.11 short tons at 2 tons/yd³.
Volume, density, and supplier units
Discuss the tonnage result with the paving contractor or plant; hot-mix asphalt is normally scheduled by weight, not by a loose cubic-yard assumption.
Field conditions that change tonnage
Compacted density, base irregularity, tapering edges, driveway aprons, handwork, and the plant's minimum load affect ordered tonnage.
Questions specific to this calculation
Which bulk density belongs in the asphalt tons estimate?
Use the finished paved length and width and the compacted design thickness. The density field must represent the asphalt mix in the supplier's quoting units.